Here's a little video showing all the key steps in the construction of my first well project in April.



First we had to cast all the concrete bricks by hand. Ox carts brought sand from the river 10 km away and we used buckets and shovels to mix the concrete on the ground before casting the bricks over a period of about two weeks. At the same time we had two guys dig the well down to the water table, and once there we constructed a cutting ring in the bottom of the well using rebar, bricks, and concrete.

After waiting a week for the concrete to dry, we continued to increase the depth of the well by digging earth out from underneath the cutting ring, which would slowly sink down as soil was removed. We managed to gain an additional meter of depth before we had to stop because soil conditions became unfavorable. We then started lining the well with the concrete bricks and backfilling between the bricks and the exposed well wall. The final step was to cast a cover for the well which would prevent debris, animals, or kids from falling in and contaminating the water.

Along the way we had several things to watch out for. Of main importance was getting the cutting ring level before we started laying bricks so that the well shaft wouldn't end up crooked. Then we had to make sure all the bricks were placed snugly together to maintain the circular shape of the shaft so not to compromise structural integrity. Vertical rebar was incorporated through the entire well and people had to be very careful not to injure themselves getting in an out of the hole. The bricks also presented issues. For instance, I found a snake curled up in the midst of the brick pile one day. Also, no one wore closed toed shoes, so everyone needed to be careful not to drop anything heavy on their feet.

There were challenges and frustrations throughout the project, but the work is done, and now the village school has a safe and reliable source of water for the kids.

I should also mention that my "job" in all of this was to help get funding, organize the project, and introduce the construction technique being used (build technical capacity). I had a guy come in from Bamako to teach the villagers how to do the work, but apart from the trainer, everyone else in the pictures was doing this kind of work for the first time.